QUESTION: Councillor C. O'Connor

"To ask the Chief Executive to detail the schedules being followed in respect of the social housing sites in Tallaght following delays occasioned by the lockdown restrictions and will he make a statement?".

REPLY:

Construction recommenced on site on the 12th April at Fernwood & Maplewood and Catherine's Row following the lifting of restrictions.  Construction commenced on site at The Weir, Whitestown Way in early May. The site at Old Bawn for age friendly housing is at detailed design stage. The delivery of the new homes on these sites have been delayed due to the restrictions and the revised timelines on each of the projects are set out below.

Construction Programme 2020-2021

Projects with Part 8 Planning Approval

Local Electoral Area

Project Name

Part 8 Approved Date

No. of Units

Current Status

 

Tallaght South

Catherine's Row, Tallaght

10/09/2018

12

Under construction. Projected delivery Q2 2022.

 

Tallaght Central

Fernwood & Maplewood

08/10/2018

40

Under construction. Projected delivery Q1 2022.

 

Tallaght Central

The Weir, Whitestown Way

10/12/2018

81

Contractor commenced on site May 2021. Projected delivery Q4 2022.

 

Tallaght Central

Old Bawn (Brady's Field)

11/02/2020

12

Detailed design underway to progress to tender Q3 2021.

 

 

 

 

145