COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, May 24, 2021
QUESTION NO. 2
QUESTION: Councillor C. O'Connor
"To ask the Chief Executive to detail the schedules being followed in respect of the social housing sites in Tallaght following delays occasioned by the lockdown restrictions and will he make a statement?".
REPLY:
Construction recommenced on site on the 12th April at Fernwood & Maplewood and Catherine's Row following the lifting of restrictions. Construction commenced on site at The Weir, Whitestown Way in early May. The site at Old Bawn for age friendly housing is at detailed design stage. The delivery of the new homes on these sites have been delayed due to the restrictions and the revised timelines on each of the projects are set out below.
Construction Programme 2020-2021 |
|||||
Projects with Part 8 Planning Approval |
|||||
Local Electoral Area |
Project Name |
Part 8 Approved Date |
No. of Units |
Current Status |
|
Tallaght South |
Catherine's Row, Tallaght |
10/09/2018 |
12 |
Under construction. Projected delivery Q2 2022. |
|
Tallaght Central |
Fernwood & Maplewood |
08/10/2018 |
40 |
Under construction. Projected delivery Q1 2022. |
|
Tallaght Central |
The Weir, Whitestown Way |
10/12/2018 |
81 |
Contractor commenced on site May 2021. Projected delivery Q4 2022. |
|
Tallaght Central |
Old Bawn (Brady's Field) |
11/02/2020 |
12 |
Detailed design underway to progress to tender Q3 2021. |
|
|
|
|
145 |
|
|