COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, May 24, 2021
QUESTION NO. 4
QUESTION: Councillor D. Richardson
"Can the Chief Executive make a report of when the new houses for Killinarden and Club House for Sacred Heart will start and report on when club house will be finished by?".
REPLY:
The procurement process for the Killinarden development commenced in July 2020. A request for final tenders is due to be published on eTenders. These tenders will then be assessed with a preferred economic operator chosen. A full report will then be brought to the Council for approval. If approved, the preferred economic operator will then have to seek planning permission. If planning permission is granted, construction will commence. At this stage, it would be anticipated that site start would be in late 2022. The build will be over a number of years with phased handover of units.