QUESTION NO. 11

QUESTION: Councillor Derren Ó Brádaigh

To ask the Chief Executive to provide a report of all Part 8's planned for the Lucan-Palmerstown-North Clondalkin Area and the timeframe for these to be delivered.

REPLY:

There are currently five projects with Part 8 approval which will deliver a total of 226 new homes from 2022. Projected delivery of these new homes is subject to works being permitted in accordance with Public Health Measures during COVID-19 pandemic.

The Council is progressing designs in relation to two further projects in the area. The first project is a proposed older persons' specific housing development at St. Ronans's Crescent, Clondalkin for approximately 10 new homes. The second project is a large mixed tenure development of social and affordable housing in Clonburris Phase 1 for a total of 265 new homes, 132 for social housing. These two proposals are projected to be brought forward to Part 8 for consideration in 2021. A programme for delivery will be set out following the Part 8 decision.

 

Part 8 Project Update

 

Project Name

TOTAL Approved Units

Status

Projected Delivery Year

 

Balgaddy

69

Tender documents being prepared for Q2 2021 tender.

2022/2023

 

St. Marks Avenue

41

Stage 4 final budget approval granted. Contractor will be appointed in 2021 once Public Health Measures permit.

2022

 

Eircom Site (Nangor Road)

93

Tender documents being prepared for Q2 2021 tender.

2022/2023

 

Lucan Road, Palmerstown (Túath Housing)

4

Detailed design underway to progress to tender by Túath Housing in Q2 2021.

2022

 

Grand Canal Lindisfarne

19

Approved at January 2021 Council Meeting.

2022/2023

 

 

226

 

 

 

 

Next tranche of Proposed Part 8’s

St. Ronans Crescent, Clondalkin

10

Proposed Older Persons specific housing progressed to ACM in November 2020

TBC

 

10

 

 

         

Large Sites/Mixed Tenure Developments

Scheme Location

Proposed no. of Units.

Tenure of Development

Current Status

Clonburris Phase 1

265

(132 Social)

Mixed Social/Affordable

Proposed mix tenure development with 132 social housing units. Architect team appointed and scheme being designed for Part 8.

 

265