COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN/PALMERSTOWN/NORTH CLONDALKIN AREA COMMITTEE
Tuesday, February 23, 2021
QUESTION NO. 11
QUESTION: Councillor Derren Ó Brádaigh
To ask the Chief Executive to provide a report of all Part 8's planned for the Lucan-Palmerstown-North Clondalkin Area and the timeframe for these to be delivered.
REPLY:
There are currently five projects with Part 8 approval which will deliver a total of 226 new homes from 2022. Projected delivery of these new homes is subject to works being permitted in accordance with Public Health Measures during COVID-19 pandemic.
The Council is progressing designs in relation to two further projects in the area. The first project is a proposed older persons' specific housing development at St. Ronans's Crescent, Clondalkin for approximately 10 new homes. The second project is a large mixed tenure development of social and affordable housing in Clonburris Phase 1 for a total of 265 new homes, 132 for social housing. These two proposals are projected to be brought forward to Part 8 for consideration in 2021. A programme for delivery will be set out following the Part 8 decision.
|
Part 8 Project Update |
|||
|
Project Name |
TOTAL Approved Units |
Status |
Projected Delivery Year |
|
Balgaddy |
69 |
Tender documents being prepared for Q2 2021 tender. |
2022/2023 |
|
St. Marks Avenue |
41 |
Stage 4 final budget approval granted. Contractor will be appointed in 2021 once Public Health Measures permit. |
2022 |
|
Eircom Site (Nangor Road) |
93 |
Tender documents being prepared for Q2 2021 tender. |
2022/2023 |
|
Lucan Road, Palmerstown (Túath Housing) |
4 |
Detailed design underway to progress to tender by Túath Housing in Q2 2021. |
2022 |
|
Grand Canal Lindisfarne |
19 |
Approved at January 2021 Council Meeting. |
2022/2023 |
|
|
226 |
|
|
|
|
|||
Next tranche of Proposed Part 8’s |
||||
St. Ronans Crescent, Clondalkin |
10 |
Proposed Older Persons specific housing progressed to ACM in November 2020 |
TBC |
|
|
10 |
|
|
|
Large Sites/Mixed Tenure Developments |
|||
Scheme Location |
Proposed no. of Units. |
Tenure of Development |
Current Status |
Clonburris Phase 1 |
265 (132 Social) |
Mixed Social/Affordable |
Proposed mix tenure development with 132 social housing units. Architect team appointed and scheme being designed for Part 8. |
|
265 |
|
|