COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN/PALMERSTOWN/NORTH CLONDALKIN AREA COMMITTEE
Tuesday, February 23, 2021
QUESTION NO. 5
QUESTION: Councillor E. O'Brien
To ask the Chief Executive for an update on the installation of automated gates at the Haydens Park entrance to Griffeen Valley Park
REPLY:
All civil works for automating the gate are complete. A completion certificate for the electrical installation is required by ESB Networks before they will connect the service. This certificate was sent to ESB Networks and despite several requests for a connection date it is not forthcoming. ESB Networks were contacted again last week to request an update which will be provided to the elected members when received.