SURFACE WATER MINOR WORKS PROGRAMME 2020 and 2021

 

Provision was made for the following surface water minor capital works and assessments to be carried out during 2020 at a cost of €435k. However with the Covid 19 situation in 2020 several of these works have had to be deferred:

Location

Project Details

Projected Exp. For 2020

Rathcoole Park

Regrade River bank to alleviate overspill during heavy rainfall migrating down to Rathcoole village. €50,000 est. At design stage. Works deferred to 2022.

€0

Tay Lane Rathcoole

Road Design required to Regrade road and allow installation of upsized Surface Water pipe. €80,000 est. At design stage.

€0

Templeogue Village Main Street

Initial assessment and feasibility for new surface water sewer – slit trenches to determine location of underground services. Works planned for early 2021.

€0

Old Lucan Road near village centre

New surface water pipeline required to facilitate road drainage. €160,000 est.   At design stage.

€0

Corkagh Park

Level Survey of existing flood alleviation works and desiltation of channels. Move project to Camac FAS.

€0

Butterfield Park

New surface water sewer required to allow separation of surface water and foul to alleviate foul sewer flooding – joint funding to be agreed with IW.   Topographical road survey to be completed in 2020 and pipeline design and tender to be advertised by end 2020.   Construction to commence in 2022.  

€2,000

Woodville/Esker Lane

New surface water pipeline required to connect road gulleys to existing surface water network.

€30,000

Cloverhill Road from Palmerstown Woods to Millford Lawns

New surface water pipeline required to provide improved connection to surface water network. Contract to be tendered and let by end 2021. Reinstatement of Road to by Roads through their improvement project. Works planned for 2021.

€25,000

Adamstown Road

Link from Castlegate to Finnstown to remove Surface Water Pumping Station. Project halted midway and with Law.

€2,000

Elkwood Park

French drain replaced in park to alleviate flooding in Knocklyon Drive. Completed August 2020

€40,000

Fortunestown Road

Relaying of surface water sewer to accommodate drainage for planned N81 cycle scheme. Completed July 2020

€42,000

Sylvan Avenue

Relocation of surface water discharge line in the road. Replacement of old damaged sewer to resolve blockage and flooding issue. Project was redesigned during construction to avoid trunk watermain that was incorrectly mapped. Project to be completed by end of 2020.

€40,000

Corner Park, Newcastle

Upsizing of diverted surface water sewer

€50,000

Idrone Knocklyon

Surface water realignment and baffle for insert into manhole to address drainage issues in Knocklyon Green and Avenue, and Delaford Lawns.

€6,000

Total

 

€237,000

Provision was made in 2020 of €250k for Flood Alleviation Minor Capital Works to address pluvial and other flooding issues at various locations. However with the Covid 19 situation in 2020 several of these works have had to be deferred:

Location

Project Details

Projected Exp. For 2020

Camac and Dodder Rivers

Clearing of fallen trees and overgrowth. Works complete.

€45,000

Poddle River

Clearing of vegetation. Works complete.

€30,000

Jobstown Stream Tributary

Camera surveys and pipe clearance on pipework and surveying from N81/Deselby to discharge to 525mm. Works to be let by end 2020.

€5,000

Owendoher Stream

Tree survey and clearing of fallen trees and overgrowth. Annual clearing works and tree survey complete.   Further tree removal on banks to be carried out as per survey recommendations.

€45,000

Oldcourt Stream

Outfall bank stabilisation works. Ecological impact assessment in progress and plan to start works by end 2020.

€45,000

Mill Ponds & Camac Screen at Toyota

Replace River Screens. Delayed until 2021 as screen design has to be approved by Camac FAS. €15,000 est.

€0

Ballycragh Lake

Clear out debris and silt from lake. Scoping to be carried out and ecological impact assessment. Deferred to 2021. €25,000 est.

€0

Telemetry installations and upgrades

2 no. further cameras to be installed to show river screens at N81 Jobstown Stream and on Camac at Mill Lane and Nangor road. Partially complete and awaiting ESB connections. Remainder of works plan to complete by end 2020.

€40,000

Total

 

€210,000

 

 

 

SURFACE WATER MINOR WORKS PROGRAMME 2021

A provision has been made for the following surface water minor capital works and assessments to be carried out during 2021 at a cost of €435k:

Location

Project Details

Projected Exp. For 2021

Templeogue Village Main Street

Initial assessment and feasibility for new surface water sewer – slit trenches to determine location of underground services

€220,000

Palmerstown Woods

New surface water pipeline required to provide improved connection to surface water network

€210,000

Rathfarnham Lake supply upgrade

Relaying of part of surface water supply pipeline in private property and installation of alarm.

€5,000

Various projects carried over from 2020 per above, to be programmed and progressed

 

 

Total

 

€435,000

The majority of the above schemes are at design stage and are subject to detailed design and full budgetary estimates.

 

A provision has been made in 2021 of €250k for Flood Alleviation Minor Capital Works to address pluvial and other flooding issues at various locations as follows:

Location

Project Details

Projected Exp. For 2021

Camac River

Clearing of fallen trees and overgrowth

€20,000

Dodder River

Clearing of fallen trees and overgrowth

€25,000

Poddle River

Clearing of vegetation

€30,000

Jobstown Stream Tributary

Upsize/replace pipework from N81/DeSelby to discharge to 525mm to remove botteneck.

€45,000

Mill ponds and Camac screen

Replace river screens

€15,000

Owendoher Stream

Clearing of fallen trees and overgrowth per tree survey 2020

€25,000

Oldcourt Stream

Outfall bank stabilisation works

€30,000

Ballycragh Lake

Clear out debris and silt from lake

€60,000

Total

 

€250,000