QUESTION NO.13
QUESTION: Councillor C. O'Connor
"To ask the Chief Executive for an update on the development of the Belgard North Link Road from Cookstown and in reporting will he confirm the schedule being followed and make a statement"
REPLY:
The revised completion date received from DBFL, the Council's Consultants for the project is the 18th December 2020.
The original completion date has not been achieved due to Covid-19 restrictions, contractor delays and additional works requirements for the future proofing of the Tallaght Public Realm Projects.