QUESTION NO. 18
QUESTION: Councillor Joanna Tuffy
To ask the Chief Executive Officer for an update on all current construction of social housing in the Lucan Electoral Area including under part 5 and any direct build or rebuilding ireland projects.
REPLY:
At present there are two developments with a total of 101 new build homes under constructon in the Local Electoral Area. These new homes will be delivered by Approved Housing Bodies between Q4 2020 and Q1 2021. There are currently no Local Authority build projects under construction within this Local Electoral Area.
The details of the schemes under construction are as follows:
LEA | Scheme Name | Total No. of Units | AHB | Details |
Fonthill-Palmerstown | Red Cow Farm, Palmerstown | 7 | Respond Housing | Currently under construction and due for delivery Q4 2020 |
Lucan | Castle View, Finnstown | 94 | Respond Housing | Currently under construction with 32 units due for delivery Q4 2020 and 62 units due Q1 2021. This scheme includes 9 Part V units. |
101 |