COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF LUCAN/PALMERSTOWN/FONTHILL AREA COMMITTEE

Tuesday, June 23, 2020

QUESTION NO. 2

QUESTION: Councillor Joanna Tuffy

To ask the Chief Executive Officer to give an update on the Celbridge Link Road and time frame and works involved and commencement date

REPLY:

The Celbridge Link Road is at pre-contract stage with contract execution to be finalised over the coming weeks. It is anticipated that construction will commence in July 2020. The project has an 18 month construction timeline.