"To ask the Chief Executive for an update on the Clondalkin Boardwalk?"

REPLY:

Clondalkin Boardwalk update to Clondalkin ACM 17.6.20

With the proximity of the boardwalk to the river and the risk this poses to the contractor, the Consultant Engineer recommended that the work be carried out in the Summer when the water levels and flow rates in the Camac are at their lowest.

The tender process which was planned for the Spring was delayed due to restrictions as result of Covid-19. The Architectural Services Department issued the tender documents to five contractors for pricing on 12th May. The contractors are due to submit their tenders by 23rd June.

It is envisaged that on successful completion of this tender process, a contractor will be recommended and appointed to carry out the works in July/August.