COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, May 25, 2020
HEADED ITEM NO. 8
HEADED ITEM: M. Staunton
Housing Supply Report Quarterly
REPLY:
Q1 2020 Housing Supply Programme Quarterly Report
2019 Total Housing Delivered |
|||||
Build |
Acquisition |
Leasing |
HAP & RAS |
Total |
|
Department of Housing, Planning and Local Government Targets |
435 |
76 |
150 |
1,053 |
1,704 |
Actual 2019 Output |
449 |
93 |
49 |
956 |
1,547 |
% |
103% |
122% |
33% |
91% |
91% |
Housing Delivered 2019 Tallaght Area |
||||||
Local Electoral Area |
Build |
Part V |
Total Build |
Total Acquisitions |
Total Leasing |
Grand Total |
Tallaght Central |
12 |
1 |
13 |
27 |
5 |
45 |
Tallaght South |
112 |
31 |
143 |
7 |
19 |
169 |
|
124 |
32 |
156 |
34 |
24 |
214 |
Total Projected Housing Delivery 2020 |
|||||||
Build |
Part V |
Total Build |
Total Acquisitions |
Total Voids |
Total Leasing |
RAS & HAP |
Grant Total Projected Delivery |
309 |
94 |
403 |
30 |
21 |
90 |
1,000 |
1, 544 |
Projected Housing Delivery Programme 2020 Tallaght Area
|
|||||
Local Electoral Area |
Build |
Part V |
Total Build |
Total Leasing |
Grand Total |
Tallaght Central |
22 |
2 |
24 |
0 |
24 |
Tallaght South |
2 |
49 |
51 |
0 |
51 |
Grand Total |
24 |
51 |
75 |
0 |
75 |
Construction Programme 2020-2021 |
||||
Projects with Part 8 Planning Approval |
||||
Local Electoral Area |
Project Name |
Part 8 Approved Date |
No. of Units Approved @ Part 8 |
Current Status |
Tallaght South |
St. Catherine's |
10/09/2018 |
13 |
St. Catherine’s is out to tender for a contractor at present. Following the tender process, a final budget submission will issue to the Department of Housing in Q2 2020. This scheme is projected to start on site in Q2 2020 subject to funding approval. |
Tallaght Central |
Fernwood & Maplewood |
08/10/2018 |
40 |
Clúid Housing have completed tender evaluation and the appointment of the contractor is imminent. Site Start Q1 2020. DHPLG funding approval granted. |
Tallaght Central |
Whitestown Way |
10/12/2018 |
81 |
Clúid Housing project site start in Q2 2020. Department of Housing funding approval granted. |
Tallaght Central |
Old Bawn (Brady's Field) |
11/02/2020 |
12 |
Part 8 report was presented to the elected members for their consideration at the February Council meeting and was approved. |
|
|
|
146 |
|
Part V Agreements in Place |
|||
Electoral Area |
Scheme Name |
Number |
Status |
Tallaght South |
“The Mews”, Citywest Village Apartments |
22 |
Part V Agreed. Units will be delivered in 2020 by Fold Housing for Older Persons Specific Housing. |
Tallaght South |
“The Meadows”, Citywest Village |
3 |
Part V Agreed. Units will be delivered in 2020. |
Tallaght South |
Cuil Dúin, Citywest |
24 |
Part V Agreed. Scheme is under construction and units will be acquired by Fold Housing for Older Persons specific housing for delivery in 2020. |
Tallaght South |
City West Village Apartments |
24 |
Part V Agreed. Units will be delivered in 2021. |
Tallaght South |
Elder Heath |
2 |
Part Vs Agreed |
Tallaght South |
Mountain Gate |
7 |
Part V Agreed |
Tallaght Central |
Kingswood |
2 |
Part V agreed. Project under construction for delivery over 2020. The total scheme of 24 units is being acquired for social housing provision by Respond! Housing. |
|
Grand Total |
84 |
|