COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN/PALMERSTOWN/FONTHILL AREA COMMITTEE
Tuesday, February 25, 2020
QUESTION NO. 23
QUESTION: Councillor Shane Moynihan
To ask the Chief Executive for a progress update on the Part 8 development at Balgaddy, and for the timeline until completion of the project.
REPLY:
A Cost Effectiveness Report on the proposed development was submitted to the Department of Housing, Planning & Local Government in November 2019. In line with the Public Spending Code, projects with an estimated cost in excess of €20m requires an economic appraisal. An estimated timeline for the completion of the project will be available when the Department of Housing, Planning & Local Government issue approval to the Cost Effectiveness Report.