MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, February 19, 2020
QUESTION NO. 7
QUESTION: Councillor F. Timmons
"To ask the Chief Executive when he will re-convene the St. Cuthbert's High Level Task Force meetings? and to also update the Committee via this question regarding any and all progress made to date, and future plans for St. Cuthbert's Park?"
REPLY:
St Cuthbert's High Level Task Force membership includes the following:
- SDCC Elected Members
- Oireachtas Members
- An Garda Síochána
- Local Safety Forum
- SDCC Senior Housing & EWCC personnel
Works carried out to date include the following:
- CCTV system installed in 2018 and commissioned in November.
- Hedge maintenance in November 2018 included the removal of vegetation, briars and rubbish in the vicinity of Kilmahuddrick Church.
- Pitch developed Spring 2019 with goal posts installed in February 2019.
- Club facilities - Clondalkin Celtic FC container moved into park July 2019.
- Houses - 63 housing units constructed in south east corner of park off Lealand Avenue 2018/2019.
- Landscaping - Area between Lealand and Lindisfarne estates landscaped following completion of housing project. Includes tree planting boundary treatment and link footpath.
- Surfacing: Entrance at Westbourne Rise resurfaced November 2019
- Boundary: Tender advertised for boundary upgrade works at Melrose Park/Deansrath Park.
Works To Do:
- Boundary - Award contract for boundary upgrade works.
It is intended to re-convene a meeting of the St. Cuthbert's High Level Task force as soon as can be arranged. In that regard, we will be shortly in contact with the Members, to identify a suitable date for all parties.