QUESTION NO. 22
QUESTION: Councillor E. O'Brien
To ask the Chief Executive to detail the next steps in the roll out of the construction of the pavilion at Griffeen Valley Park, in particular can you advise the number of submissions received during the public consultation period and when it is anticipated that construction will commence on the pavilion.
REPLY:
The Part 8 for the Pavillion at Griffeen Valley Park has been completed with 4 submissions received during the public consultation period as outlined in the CE report. The next step is completion of the detailed design and construction stages. A framework for contractors for Design and Build Contracts is available to the council for construction of pavillions; so this facilitates some efficiency here. It is envisaged that the contractor will be appointed in Q1 2020 at which stage the detailed design and construction stage will commence.