COMHAIRLE CHONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE 1
Monday, March 20, 2006
QUESTION 16
QUESTION: Cllr. Karen Warren
"To ask the Manager to state when the temporary traffic calming measures on Fettercairn Road will be removed in favour of the permanent measures that were promised when the new housing along Fettercairn Road was recently constructed, the likely time when such measures will be installed and if he will make a statement on the matter?"
REPLY
The temporary ramps on the
The proposed traffic calming measures for the internal estate roads of the adjoining estates have been completed. The Consultant Architect has confirmed that the works on traffic calming of the main distributor road are ongoing and are scheduled for completion over the coming weeks.
It is anticipated to hand over the remaining 9 outstanding units at the end of March 2006.