QUESTION NO. 2

QUESTION: Councillor E. Higgins

"To ask the Chief Executive for an update on the programme of works for Corkagh Park?"

REPLY:

An update on Corkagh Park projects listed in the 2019 Improvement Works Programme is set out in the table below.

No

Description

STATUS

1

Provision of vehicle & pedestrian gate to Oak Avenue entrance off Green Isle Road

Materials are being procured for project with gate fabrication to occur during winter months.

2

Widen cycle path from Fonthill Rd to Kavanaghs Bridge (near allotments)

Path has been widened and a contract has been awarded to surface the path in November.

3

Upgrade access road to allotments to include surfacing and fencing

A contract has been awarded to surface the road in November. Fencing is in production and will be installed in November/December.

4

Surface section of path at NE end of lake near walled garden

A contract has been awarded to surface the path in November.

5

Watercourse upgrade works

Silt has been removed from the Powder Mills pond. Vegetation will be cut back in week 43. Pond will be filled thereafter.

6

Replace K-barrier with kissing gate at Cherrywood Crescent entrance to park

Kissing gate has been manufactured. Installation to occur in November.