COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, April 15, 2019
QUESTION NO. (6)
QUESTION: Councillor C. O'Connor
To ask the Chief Executive to present an update on the progress of the building programme at the new Castletymon Library; will he confirm the schedule now being followed and detail any contacts he has had with the local community in respect of the matter and will he make a statement.
REPLY:
"The contractor started work on the Castletymon library project on 7th January 2019. Site set-up is completed along with site clearance and service water diversion. There was a four week delay from Irish Water for water main diversion work but this is now progressing. The foundation sub-structure work is in progress and as per the schedule, site handover is expected by the end of the year. Any issues/concerns raised by the public have been dealt with by the relevant departments."