Both these estates are developed by the same developer. Dodderbrook Phase 1 PL is snagged and connected.
The original designs for both were agreed in mid 2018 and the PL installation proceeded on that basis. However, when called to inspect the sites, it transpired that the physical layouts of both Dodderbrook Phase 2 and Ballycullen Green were substantially different to those originally agreed. As a result, a partial redesign of the PL is currently ongoing with the developer.
SDCC are currently trying to expedite this process.