COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF RATHFARNHAM/TEMPLEOGUE-TERENURE AREA COMMITTEE

Tuesday, March 12, 2019

QUESTION NO. 8

QUESTION: Councillor D. Looney

"To ask the Chief Executive to provide an update on all remaining playspace and teen space programme works in the area under the remit of this Committee, including a projected timeline for such?"

REPLY:

The proposal in relation to the provision of teenage facilities has recently being approved by the Council with capital funding also being approved. In 2019 it is intended to progress the projects at the following locations:

In relation to the RTT area the proposal is as follows:

Ballycragh Park: It is proposed to augment the facilities at this location to allow for a formal activity area for teenagers wit equipment designed for use by older children. Seating and Wi-Fi is to be incorporated into the plans. The estimated cost is €110,000.

The project is at an early design stage. Therefore the programme cannot be fully confirmed as yet. However an outline stage programme is as follows: The preliminary design for this project is underway. Once completed it will be subject to detailed design and the required procurement and tender processes. Subject to successful procurement processes the programme for construction will be agreed with the successful contractor. Public Realm are currently in discussions with the Broadband Officer in relation to accessing grants to provide broadband access.

Playspace programme:

The playspace programme is nearing completion and the following projects are at construction phase with the contractor appointed and works will be completed within the coming weeks: Whitechurch (substantially complete), Tymon Park-Limekiln and Glendown open space. The proposed design for Delaford is being considered in the context of the proposed adjacent school. Both Greenhills Park and Perrystown playgrounds are at tender stage with tenders received and being assessed. Subject to successful tender processes a contractor will be appointed shortly to both and construction programme can then be agreed.

Other playgrounds: