COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF RATHFARNHAM/TEMPLEOGUE-TERENURE AREA COMMITTEE
Tuesday, February 12, 2019
QUESTION NO. 7
QUESTION: Councillor E. Murphy
"I am requesting a full update on the situation at the Primary Care Centre for Ballyboden. Can the Council please provide a full update on the situation as residents are extremely anxious about the situation as this proposed development is now on the agenda for six years with no visible progress made.
To ask the Chief Executive for the update to include a full traffic management report, a proposed start date, an estimated completion date and details on all services to be provided in the Centre?"
REPLY:
Under Register Reference SD13A/0222 (ABP ref. PL 06S.2436220) permission was granted to the HSE for a Primary Care Centre in Ballyboden at lands adjoining St. Augustine’s Priory, Edmondstown Road, Dublin 16 on 31st December 2014. The timing of construction is a matter for the HSE. However, the Planning Department made contact with the HSE and have been advised that the HSE are progressing a sale and leaseback of the site with construction anticipated to commence mid 2019 with completion by end 2020, early 2021.