QUESTION NO. 13

QUESTION: Councillor E. O'Brien

"To ask the Chief Executive to indicate if a timeline has been established for the follow up Part 8 in relation to the Lucan Village Improvement Scheme?"

REPLY:

We are shortly to commence the procurement process for a consultant engineer to;

1. Commence final design documentation for the Lucan Bridge Plaza (The Weir).

2. Complete Revised Part 8 process for Lucan Village Green.

3. Compile tender/contract documents for both the above schemes.

It is hoped to be in a position to go to public consultation on the revised Part 8 above in late Spring 2019. It is foreseen that both schemes will be included in the same works contract and, pending a successful Part 8, will go out to tender towards the end of this year, resources permitting.