COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF CLONDALKIN AREA COMMITTEE

Wednesday, January 16, 2019

QUESTION NO. 19

QUESTION: Councillor M. Ward

''To ask the Chief Executive to give an update of the timeline involved in the development of the new North Clondalkin library?"

REPLY:

"North Clondalkin Library is progressing to the agreed programme. Concrete columns and walls have reached the main roof and first floor level, with blockwork progressing in January. The construction period has been set at 18 months as part of the contract, but it is anticipated that it may take 15 months to construct if there are no delays".