DEVELOPMENT CONTRIBUTION SCHEME INDEXATION
REPLY:
INDEXATION OF DEVELOPMENT CONTRIBUTION SCHEME
Section 48 Development Contribution Scheme
The Council’s Section 48 Development Contribution Scheme 2016-2020 adopted by the Council at its meeting on 14th December 2015 included the following provision:-
Indexation in accordance with the Tender Price Index may be applied to be effective from 1st January 2018 for permissions granted after this date, having regard to the prevailing economic circumstances, subject to the approval of the Council. The Scheme provides thereafter for the application of annual indexation increases.
The current levy rates are:-
Residential Development € 90.42 per sq metre
Industrial/Commercial Development € 79.73 per sq metre
Levies collected under the Section 48 Scheme fund the following classes of infrastructure and facilities
Class of Public Infrastructural Development |
Class 1: Roads infrastructure & facilities |
Class 2: Surface Water & Environment infrastructure & facilities |
Class 3: Community facilities & amenities |
Class 4: Parks and open spaces facilities & amenities |
Class 5: Economic, Enterprise and Tourism Development including Libraries |
|
The basis for applying an increase effective from 1st January 2019 is that construction tender prices have continued to rise since their lowest point in 2010, the annual rate of increase was 5.6% in 2016 with an increase of 6.3% for 2017 and 7.2% for 2018. These increases will bring construction prices back to the level they were at in 2004 and relate to the increased level of activity in the industry.
Recommendation
With the approval of the Elected Members, it is proposed that an indexation rate of 7.2% will be applied only to Industrial/Commercial Development and will become effective on permissions granted after 1st January 2019. This will increase the levy as follows:-
Industrial/Commercial Development € 85.47 per sq metre