COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF TALLAGHT AREA COMMITTEE
Monday, November 26, 2018
QUESTION NO. 18
QUESTION: Councillor C. O'Connor
"To ask the Chief Executive to confirm the schedule now being followed in respect of housing developments in Tallaght which were the subject of recent Part 8 decisions; will he give details in each case and will he make a statement?"
REPLY:
Scheme |
No. of Units |
Planning Status |
Next Stage |
St. Catherine’s Knockmore |
13 |
Part 8 approved September 2018. |
Pre-Tender Design to be prepared |
Fernwood and Maplewood |
40 |
Part 8 approved October 2018 |
Clúid Housing are currently preparing pre tender design for both schemes. |
Whitestown Way, Tallaght |
81 |
Part 8 consultation complete and County Architects being prepared for December Council meeting |
Part 8 report to be presented to Council on the 10th of December 2018 |