COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN AREA COMMITTEE
Tuesday, October 23, 2018
QUESTION NO. 4
QUESTION: Councillor P. Gogarty
"To ask the Chief Executive for an update on footpath repair schedules in this electoral area for the past six months and for the coming six months?"
REPLY:
Path repair works in the Lucan Area are proceeding in accordance with the 2018 Roadworks Programme submitted earlier in the year.
In summary, scheduled repairs are complete in the following areas: The Dingle/Coppice, Hollyville Lawn, Old Lucan Road (Palmerstown), Chalet Gardens, Wheatfield Road, Arthur Griffith Park, Airlie Heights, Palmerstown Green.
Works are ongoing in the following areas and are scheduled to complete in November 2018: Whitethorn Estate, Wheatfield Estate, Palmerstown Woods, Kennelsfort Road, and Earlsfort Estate.
Further works will be carried out under the 2019 Roadworks Programme. This is currently being compiled and will be submitted to the members on completion.