MOTION NO. 2
MOTION: Councillor L. O'Toole
That this Area Committee requests the Chief Executive provide an update on housing in Adamstown SDZ regarding social and affordable. To include a breakdown of style, size, location and time line for commencement and completion.
REPORT:
Within Adamstown SDZ the Council are engaging with three developers in respect of the various tiles within the SDZ. Currently there are 110 units under construction which are scheduled for delivery between Quarter 4 2018 and Quarter 1 2019. Engagement is continuing with developers in respect of subsequent planning permissions however no agreements are in place at present to set out the next phase of Part V's due for delivery within Adamstown SDZ. The breakdown on units due for delivery over the coming months are set out as follows:
Type | No. of Units | Number of Bedrooms | Location | Projected Completion |
Semi-detached House | 3 | 3 | Shackleton Phase 1 | November 2018 |
Semi-detached House | 32 | 3 | Somerton Phase 1 | Late 2018/Early 2019 |
Semi-detached House | 7 | 3 | St. Helens Phase 1 | Late 2018/Early 2019 |
Apartment | 3 | 3 | Shackleton Phase 1 | Late 2018/Early 2019 |
Duplex | 4 | 3 | Shackleton Phase 1 | Late 2018/Early 2019 |
Apartment | 10 | 1 | Shackleton Phase 1 | Late 2018/Early 2019 |
Apartment | 48 | 2 | Shackleton Phase 1 | Late 2018/Early 2019 |
Duplex | 3 | 2 | Shackleton Phase 1 | Late 2018/Early 2019 |
110 |