QUESTION: Councillor D. Looney
"To ask the Chief Executive for an update on all social housing schemes currently under way or being planned in the area under the remit of this Committee, and to make a statement on the matter?"
REPLY:
There are currently two schemes under construction on the first tranche of social housing build programme within the Local Electoral Area. A total of 64 units will be delivered over Quarter 4 2018 and early Quarter 1 2019 in Killininny and Ballyboden.
There are three proposed schemes in the next tranche of housing construction programme with approximately 90 units. One project at Homeville has received Part 8 approval and the next two projects at Knocklyon, Ballycullen and Stocking Lane, Rathfarnham are at early stage design and feasibility pre Part 8 stage.
Electoral District | Schemes | No. of Units | Status |
Rathfarnham/Templeogue/Terenure | Killininny, Co Dublin | 24 | Under Construction. Due for completion Quarter 4 2018 |
Rathfarnham/Templeogue/Terenure | Ballyboden, Rathfarnham | 40 | Under Construction. Due for completion Quarter 4 2018 |
Rathfarnham/Templeogue/Terenure | Homeville | 16 | Part 8 approved September 2018. Design team to be appointed pre-tender |
Rathfarnham/Templeogue/Terenure | Knocklyon, Ballycullen | 40 | Preliminary designs and feasability being carried out |
Rathfarnham/Templeogue/Terenure | Stocking Lane | 40 | Preliminary designs and feasability being carried out |