"To ask the Chief Executive for an update on the River Poddle Flood Alleviation Scheme, and to make a statement on the matter?"

REPLY:

The River Poddle FAS commenced in March 2018 following the appointment of Nicholas O'Dwyer Consulting Engineers and has a current projected completion date of Q3 2022. The scheme which if funded by the OPW is progressing and currently sits in Stage (i) Preliminary Design Stage, the consultants are currently working on the hydraulic model and Environmental reports. A presentation on the current status of the scheme will be given to the October 2018 RTT ACM under a Headed Item