COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN AREA COMMITTEE
Tuesday, September 25, 2018
QUESTION NO. 3
QUESTION: Councillor D. O'Brien
"To ask the Chief Executive to give an update on the Public Realm Improvement Programme 2018 that was given to this committee in January. This report will give an update on all work that has been carried out so far and a start and finish date for work that has not been completed yet."
REPLY:
An update on the 2018 Improvement Works Programme is set out in the table below.
No |
Location |
Description of Works |
Status |
1 |
Griffeen Valley Park |
Automate Haydens Lane car park gates |
At tender preparation stage |
2 |
Dispensary Lane |
Phase 2 - Upgrade steps outside Health Centre |
Handrail to be installed in October & ramp to be completed. Steps to commence in Q4. |
3 |
Mount Andrew Open Space |
Pitch drainage scheme |
Complete |
4 |
Waterstown Park |
Provision of Dog Run |
Complete, awaiting signage before opening. Due in October. |
5 |
Waterstown Park |
Drainage works near fitness equipment |
Complete |
6 |
Willsbrook Park |
Drainage works |
Complete |
7 |
Beech Park |
Public Lighting from Cherbury to Beech Park estate |
Complete |
8 |
Esker Cemetery |
Provision of automated car park gate & boundary treatment |
Gate at tender preparation stage. |
9 |
Adamstown Roundabout |
Landscaping works |
To be complete in Q4 during planting season. |
10 |
Griffeen Valley Park |
Automate Newcastle Rd car park gates |
A tender preparation stage |
11 |
Griffeen Valley Park |
Seating in south side of park |
To be installed in Q4 |
12 |
Griffeen Valley Park |
Upgrade dog run (seating and entrances) |
Entrance upgraded. Seat to be installed in Q4 |
13 |
Ballyowen Park |
Install link footpath at Fonthill Road entrance |
Path installed. To be tarmacked in Q4 |
14 |
Glenaulin Park |
Regrade & drain GAA pitch + goal posts |
Tendered |
15 |
Colthurst Open Space |
Path across open space along desire line to link with Rochford Avenue |
Path installed. To be tarmacked in Q4 |
16 |
Lucan Weir |
New vehicle access gate |
Fabricated. To be installed in October. |
17 |
Abbeywood Court |
Boundary fence at Glenvale end of open space |
Order issued. To be installed in October. |
18 |
Lucan Demesne |
Upgrade boundary wall with N4 slip road + provision of benches |
Benches installed. Boundary wall to be progressed in Q4. |