QUESTION: Councillor D. O'Brien
"To ask the Chief Executive for an update on the Lucan swimming pool. How much progress has been made on this since the last area committee?"
REPLY:
The main contractors stage 2 tender for the Lucan Swimming Pool was published on 8th August 2018 with a closing date for receipt of tenders on Monday 24th September. This will be followed by a tender assessment process which will take approximately three weeks resulting in a preferred bidder. An additional tendering process for the associated specialist contracts is also being prepared and should be completed by November 2018.
A report will then be submitted to the Department of Transport, Tourism and Sport for approval to proceed with the appointment of the contractors to move the project on to the construction phase.