QUESTION NO. 7
QUESTION: Councillor E. Murphy
"To ask the Chief Executive to please provide an update on the progress of the Programme of Works for Rathfarnham Templeogue Terenure which was present to the Area Committee previously in 2018?"
REPLY:
A summary of the current position on public realm improvement works schemes in the Rathfarnham/Templeogue-Terenure area for 2018 is as set out below.
RATHFARNHAM TEMPLEOGUE TERENURE AREA |
|
|
Ellensborough Estate |
Install railing on top of boundary wall at Ellensborough Lawn |
Tender process completed, awaiting confirmation of start date from contractor |
Rushbrook entrance to Tymon Park |
Automate main entrance to Tymon Park |
Proposal received from the Council's gate automation contractor. Application for connection to power supply has been submitted. |
Dolly's Field, Moyville Estate |
Construct perimeter footpath |
Not yet commenced, preparation of sub-base due to start during week commencing 10 Sept. Tender process has been completed for footpath surfacing works. |
Beechfield Park |
Carry out improvements to tennis and basketball courts. |
Not yet commenced |
Park Avenue to Grange manor |
Plant hedging along boundary wall |
Will take place during the planting season in November/December. |
Knocklyon Park |
Construct remaining length of footpath to create looped walk |
Not yet commenced, preparation of sub-base due to start during week commencing 10 Sept. Tender process has been completed for footpath surfacing works. |
Wellington Lane to Glendown Estate |
Install public lighting scheme on walkway along the Poddle river |
Scheme is being progressed by the Council's Public Lighting Section. |
Tymon Park |
Carry out improvements to the dog run |
Drainage works and relocation of entrance gate are both completed. |
Wainsfort Manor Crescent / Green |
Provide tarmac surface to existing gravel path across the green space |
Tender process completed for surfacing works. These will take place on this and other footpath schemes in October/November. |