"That this Area Committee ask the Chief Executive why it has taken so long to carry out the works at the Glenmaroon entrance to Glenaulin Park and why is it that it is still in a very unsatisfactory state, even worse than when work got under way (it was very bad then) and can he confirm a date when residents can expect it to be at a satisfactory standard."

REPORT:

The completion of the works was initially delayed due to the storms earlier in the year.
Once the drainage works were completed, the Drainage section sought to coordinate the final reinstatement with the Public Realm section.
Unfortunately, it is not currently the appropriate time for the planting in this location to be carried out.
The Drainage section has now proceeded and carried out the reinstatement on all matters that can be completed.
Public Realm will revisit the area during the appropriate planting season and carry out the remaining works.