QUESTION NO. 8

QUESTION: Councillor M. Ward

"To ask the Chief Executive for a report on the progress of new developments in the Clondalkin Lea at Mayfield, Lett's Field, St Mark's,  St Cuthbert's, PPP Kilcarbury, Oldcastle and The Grange and to give a statement on this?"

REPLY:

There are three construction schemes currently on site at various stages of completion. The scheme at St. Cuthbert's is awaiting final budget approval from the Department of Housing and is estimated to have a site start in July 2018. The table below sets out the estimated completion months for handover from the contractor to the Council for tenanting:

Electoral District Schemes Funding Programme No. of Units Status Due for completion
Clondalkin St Mark's Green, Clondalkin SHCIP 11 On Site April 2017 August 2018
Clondalkin Mayfield Estate SHCIP 17 On Site February 2017 June 2018
Clondalkin St. Cuthbert's, Clondalkin SHCIP 63 Final Budget Approval Pending - Estimated Site Start July 2018 2nd Quarter 2019
Clondalkin Letts Field, Neilstown, Clondalkin SHCIP 37 On Site 4th Quarter 2019
      128    

On the next tranche of proposed social housing projects there are 6 sites identified which are at early stages of feasibility. Once these sites have completed feasibility and are determined suitable for social housing developments the proposed schemes will be designed and commence the Part 8 planning process over the coming 12 months.

Electoral District Location Indicative Numbers Current Status
Clondalkin St. Mark's Avenue, Clondalkin 39 Stage 1 Approved. Project to be developed to design/planning stage
Clondalkin Oldcastle 50 Feasibility being carried out
Clondalkin Eircom Site 50 Currently with the Office of Government Procurement for a Design Team
Clondalkin Riversdale, Clondalkin 15 Feasibility & Designs Being Prepared
Clondalkin Collinstown Grove, Clondalkin (2 Sites) 12 2 Sites - to be advertised through Expression of Interest to Approved Housing Bodies
    166  

In relation to Kilcarbury, the final tenders are due back on the 18th June they will then be evaluated with the preferred candidate to be chosen by the end of the Summer.