COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF RATHFARNHAM/TEMPLEOGUE-TERENURE AREA COMMITTEE
Tuesday, June 12, 2018
QUESTION NO. 15
QUESTION: Councillor D. Looney
"To ask the Chief Executive for an update on the Wellington-Whitehall cycle scheme and the Dodder Greenway, and to make a statement on the matter?"
REPLY:
"The procurement of a consultant for the Wellington-Whitehall cycle scheme is progressing and it is expected that it will be advertised in June 2018 with the consultant commencing in August 2018, with a Part 8 being advertised in Oct/Nov 2018. The procurement of a consultant for the Dodder Greenway cycle scheme is progressing and it is expected that it will also be advertised in June 2018, with the consultant commencing the detailed design and tender documents in August 2018. As ERDF funding has already been secured, we are hopeful that elements of the scheme will commence construction in 2019."