COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL

South Dublin County Council Crest

MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, June 11, 2018

QUESTION NO.4

QUESTION: Councillor D. Looney

To ask the Chief Executive for an update on the Council’s social housing build and purchase programme, and to make a statement on the matter. 

REPLY:

Construction Programme Update

The next tranche of social housing build projects has commenced with 2 Part 8's published in April and May with an indicative number of 26 units in total. There are a further 7 proposed schemes as presented at Area Committee Meetings which are currently under review with proposed plans being developed for Part 8 publication from Q2 2018 to Q2 2019. There will be approximately 280 units over these 9 schemes being brought through the Part 8 planning process up to May 2019.

Electoral Area Site Location Indicative No.s Status
Rathfarnham/Templeogue/Terenure Homeville 16 At Part 8 Consultation Stage    
Tallaght St. Catherines Knockmore 10 Part 8 Consultation to commence 31st May 2018
    26  

There are currently 9 schemes under construction with a further 1 scheme due to commence in June 2018. These 10 schemes will deliever 351 housing units from June 2018 to June 2019. The breakdown of the schemes across the county are listed below:

Electoral District Schemes No. of Units Status
Clondalkin St Marks Green, Clondalkin 11 On Site April 2017
Tallaght McUilliam (Fortunestown) 28 On Site May 2017
Clondalkin Mayfield Estate 17 On Site February 2017
Tallaght Dromcarra, Tallaght 14 On Site May 2017
Tallaght St. Aidans, Tallaght = Social + TAP 90 On Site August 2017. Partial Handover June 2018 of 47 units.
Rathfarnham/Templeogue/Terenure Killininny, Co Dublin 24 On Site Jan 2018
Clondalkin St. Cuthberts, Clondalkin 63 Due to commence June 2018
Clondalkin Letts Field, Neilstown, Clondalkin 37 On Site
Rathfarnham/Templeogue/Terenure Ballyboden, Rathfarnham 40 On Site Nov 2017
Tallaght Killinarden, Tallaght 27 On Site October 2017
    351  

Acquisition Programme Update

The Council are working directly with the Housing Agency to acquire social housing units in addition to a small number of direct housing acquisitions and Part V acquisitions. The Council is focused on housing delivery through the house build programme and turnkey opportunities as they arise. During 2018 we have programmed to acquire a total of 31 housing units under direct acquisitions, housing agency acquisitions and Part V acquisitions as set out below.

LA Acquisitions Breakdown
  2017 Delivered Q1 2018 Q2 2018 Q3 2018 Q4 2018
SDCC Acquisitions 26 1 0 10 0
Housing Agency Acquisitions 6 4 2 0 5
Part V Acquisitions 10 1 8 0 0
  42 6 10 10 5