MEETING OF LUCAN AREA COMMITTEE

Tuesday, April 24, 2018

MOTION NO. 10

MOTION: Councillor W. Lavelle

"That this Area Commitee requests the Chief Executive to present a detailed status update on all projects committed to as part of the 2017 Public Realm works programme but which were not completed last year and are still outstanding."

REPORT:

An update on projects from the 2017 Improvement Works Programme is set out in the table below.

No

Location

Description of Works

Status

1

Griffeen Valley Park

Automate Hayden’s Lane car park gates

To be tendered as part of the 2018 Improvement Works Programme.

2

Griffeen Valley Park

Footpath improvement near playground

Footpath widened. Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2.

3

Dispensary Lane

Upgrade steps outside Health Centre

Under construction.

4

Hermitage Park

Car park extension

Site to be used as compound during construction of Frame Football facility. Car park works to be progressed thereafter.

5

Mount Andrew Open Space

Pitch drainage scheme

To be undertaken in Q3 once outfall is in place.

6

Arthur Griffith Estate

Surface paths on open space

Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2.

7

Waterstown Park

Provision of Dog Run

Order issued to install. Expect contractor to be on site in June.

8

Waterstown Park

Drainage works near fitness equipment

To be completed in Q2.

9

Willsbrook Park

Entrance upgrade at Esker Lane, surfacing works around benches

Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2.

10

Willsbrook Park

Drainage works

To be undertaken in Q3 as part of the Mount Andrew open space drainage contract.

11

Beech Park

Public Lighting from Cherbury to Beech Park estate

Civil works to commence by June.

13

Esker Cemetery

Provision of automated car park gate & boundary treatment

Boundary treatment complete. Provision of automated car park gate to be tendered as part of 2018 Improvement Works Programme.

14

Adamstown Roundabout

Phase 2

To be undertaken in Q4 as part of the 2018 Improvement Works Programme.