An update on projects from the 2017 Improvement Works Programme is set out in the table below.
No |
Location |
Description of Works |
Status |
1 |
Griffeen Valley Park |
Automate Hayden’s Lane car park gates |
To be tendered as part of the 2018 Improvement Works Programme. |
2 |
Griffeen Valley Park |
Footpath improvement near playground |
Footpath widened. Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2. |
3 |
Dispensary Lane |
Upgrade steps outside Health Centre |
Under construction. |
4 |
Hermitage Park |
Car park extension |
Site to be used as compound during construction of Frame Football facility. Car park works to be progressed thereafter. |
5 |
Mount Andrew Open Space |
Pitch drainage scheme |
To be undertaken in Q3 once outfall is in place. |
6 |
Arthur Griffith Estate |
Surface paths on open space |
Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2. |
7 |
Waterstown Park |
Provision of Dog Run |
Order issued to install. Expect contractor to be on site in June. |
8 |
Waterstown Park |
Drainage works near fitness equipment |
To be completed in Q2. |
9 |
Willsbrook Park |
Entrance upgrade at Esker Lane, surfacing works around benches |
Order issued to surface in 2017 but put on hold pending suitable ground conditions. Expect completion in Q2. |
10 |
Willsbrook Park |
Drainage works |
To be undertaken in Q3 as part of the Mount Andrew open space drainage contract. |
11 |
Beech Park |
Public Lighting from Cherbury to Beech Park estate |
Civil works to commence by June. |
13 |
Esker Cemetery |
Provision of automated car park gate & boundary treatment |
Boundary treatment complete. Provision of automated car park gate to be tendered as part of 2018 Improvement Works Programme. |
14 |
Adamstown Roundabout |
Phase 2 |
To be undertaken in Q4 as part of the 2018 Improvement Works Programme. |