QUESTION NO.3

QUESTION: Councillor E. O'Brien

To ask the Chief Executive to detail the number of Part 8 Housing schemes currently under construction in the County and the number of Part 8 schemes it is anticipated will be commenced before the end of 2019?

REPLY:

To date there are nine Part 8 housing development schemes currently under construction as detailed below:

Scheme

No. of units

Development Type

Mayfield Estate, Clondalkin

17

Traditional

St. Marks Green, Clondalkin

11

Traditional

Dromcarra, Tallaght

14

Traditional

MacUilliam (Fortunestown)

28

Traditional

Killininny, Co. Dublin

24

Rapid build

Killinarden, Tallaght

26

Traditional

Letts Field, Neilstown, Clondalkin

37

Traditional

Ballyboden/Owendoher, Rathfarnham

40

Traditional

St. Aidans, Tallaght

90

Rapid Build

 

287

 

 It is anticipated that St Cuthberts which will deliver 63 Units will start on site in the coming weeks.

With regard to proposed Part 8 schemes for possible construction commencement before end 2019, a list of proposed schemes were presented to the relevant Area Committees in February.  When these designs are  developed, they will be presented again to the Area Committees by way of Part 8 Planning Process.