QUESTION NO.3
QUESTION: Councillor E. O'Brien
To ask the Chief Executive to detail the number of Part 8 Housing schemes currently under construction in the County and the number of Part 8 schemes it is anticipated will be commenced before the end of 2019?
REPLY:
To date there are nine Part 8 housing development schemes currently under construction as detailed below:
Scheme |
No. of units |
Development Type |
Mayfield Estate, Clondalkin |
17 |
Traditional |
St. Marks Green, Clondalkin |
11 |
Traditional |
Dromcarra, Tallaght |
14 |
Traditional |
MacUilliam (Fortunestown) |
28 |
Traditional |
Killininny, Co. Dublin |
24 |
Rapid build |
Killinarden, Tallaght |
26 |
Traditional |
Letts Field, Neilstown, Clondalkin |
37 |
Traditional |
Ballyboden/Owendoher, Rathfarnham |
40 |
Traditional |
St. Aidans, Tallaght |
90 |
Rapid Build |
|
287 |
|
It is anticipated that St Cuthberts which will deliver 63 Units will start on site in the coming weeks.
With regard to proposed Part 8 schemes for possible construction commencement before end 2019, a list of proposed schemes were presented to the relevant Area Committees in February. When these designs are developed, they will be presented again to the Area Committees by way of Part 8 Planning Process.