MOTION NO. 307

MOTION: Councillor E. O'Brien

That no house, apartment, duplex or other residential unit or commercial or other building constructed in phase 2 of the development be occupied until commencement of the DART expansion and electrification of the Dublin/ Hazel Hatch rail route. Table 4.3 to be amended

REPORT:

In the context that the subject SDZ Lands are already relatively well serviced by public transport and road infrastructure, it is recommended that the wording of the proposed motion be amended to ensure that is does not unnecessarily delay the delivery of housing and associated transport infrastructure.

A submission from the NTA on the Draft Planning Scheme confirms that the NTA is committed to deliver the level of additional public transport infrastructure required to serve Clonburris as identified under the Transport Assessment and Strategy for the Draft Planning Scheme. The Transport Assessment indicates that the DART Underground will be delivered between 2026 and 2035. The submission of the NTA states that it is intended to complete the BusConnects Programme by 2019 including aspects that will cater for the demands of the SDZ Planning Scheme.

Further to additional correspondence (January 2018), the NTA advises that

he exact timing of the DART Expansion Programme will be influenced by the Government’s 10 year Capital Plan, which is expected to be announced shortly.

The provision of the DART Expansion, although desirable for the enhancement of public transport facilities directly serving Clonburris in the medium and long term, are of such a scale in capacity terms that the development of Clonburris is not dependent on their completion. The modelled 2026 scenario in the Transport Assessment and Strategy demonstrates that the early delivery of the DART Expansion is not required.

Section 4 of the Draft Planning Scheme details the Phasing Programme for the development of the lands. The Phasing Programme aims to provide a balanced delivery of infrastructure, urban centres and community services in tandem with population increase through a logical flexible schedule.

Current policy and legislation provides the context for the phasing approach the subject lands:  

The subject motion is one of a number of motions proposing to amend Table 4.3 of the Scheme to link various transport infrastructure, predominantly individual planned public transport projects, and the delivery of residential units. The Transport Assessment and Strategy that accompanies the Draft Planning Scheme outlines that the Orbital Bus Route and the DART Underground/Expansion as well as additional local and secondary orbital bus routes will serve the trip demands of the Draft Planning Scheme.

As a summary, the Chief Executive outlines that the Lucan and Clondalkin area will benefit from the planned future public transport and the Draft Planning Scheme does not phase development in the Clonburris SDZ with the delivery of planned public transport for the following reasons:

Within the context of the above, the proposed motion could delay or inhibit the delivery of housing required by the Core Strategy of the County Development Plan and supported by national policy and legislation.

The intention of the motion is noted and it is therefore recommended that the additional wording be added as a Key Principle under the Movement and Transport Section (2.2).

Recommendation

It is recommended that this motion is adopted with amendment.

Insert the following additional text as a Key Principle under Section 2.2.1 of the Planning Scheme:

To seek the delivery of public transport infrastructure, rail, orbital bus, radial bus and local bus services, in conjunction with the NTA that will serve the trip demands of the SDZ Planning Scheme..

Strategic Environmental Assessment of Chief Executive’s Recommendation

No interaction with Strategic Environmental Objectives.

Appropriate Assessment Screening of Chief Executive’s Recommendation

No likely significant effects on European sites within the SDZ’s zone of influence are predicted.