QUESTION NO.13

QUESTION: Councillor F. Timmons

To ask for a report into the Village Initiative Scheme and outline by Electoral area what progress has been made and what work is outstanding and estimated timeframe's for same ?

REPLY:

Village

Electoral Area

Status

 

 

 

Palmerstown Village/Manor Road

Lucan

Completed 2015

Limekiln Green

Templeogue Terenure

Completed 2015

Rathcoole

Clondalkin

Completed 2016

Newcastle Phase 1 -

Aylmer Rd

Clondalkin

Completed 2016

Rathfarnham Village Phase 1  - Gateway Plaza

Rathfarnham

Completed 2016

Newcastle Phase 2 -

Newcastle Lyons Gateway

Clondalkin

Completed 2016

Belgard Walkway

Tallaght Central

Completed 2016

Tallaght Village Phase 1

Old Greenhills Rd/Old Bawn Rd

Tallaght Central

Under construction. Will be complete by end of Jan 2018

Templeogue Village

 

Templeogue Terenure

Part VIII in progress. Due for Public Consultation in Spring 2018

Saggart Village

Tallaght Central

For tender in Spring 2018

Lucan Village Green/Lucan Bridge Plaza

Lucan

Design under revision to include footbridge.

Revised Part VIII in Summer 2018