QUESTION NO.13
QUESTION: Councillor F. Timmons
To ask for a report into the Village Initiative Scheme and outline by Electoral area what progress has been made and what work is outstanding and estimated timeframe's for same ?
REPLY:
Village |
Electoral Area |
Status |
|
|
|
Palmerstown Village/Manor Road |
Lucan |
Completed 2015 |
Limekiln Green |
Templeogue Terenure |
Completed 2015 |
Rathcoole |
Clondalkin |
Completed 2016 |
Newcastle Phase 1 - Aylmer Rd |
Clondalkin |
Completed 2016 |
Rathfarnham Village Phase 1 - Gateway Plaza |
Rathfarnham |
Completed 2016 |
Newcastle Phase 2 - Newcastle Lyons Gateway |
Clondalkin |
Completed 2016 |
Belgard Walkway |
Tallaght Central |
Completed 2016 |
Tallaght Village Phase 1 Old Greenhills Rd/Old Bawn Rd |
Tallaght Central |
Under construction. Will be complete by end of Jan 2018 |
Templeogue Village
|
Templeogue Terenure |
Part VIII in progress. Due for Public Consultation in Spring 2018 |
Saggart Village |
Tallaght Central |
For tender in Spring 2018 |
Lucan Village Green/Lucan Bridge Plaza |
Lucan |
Design under revision to include footbridge. Revised Part VIII in Summer 2018 |