MEETING OF LUCAN AREA COMMITTEE

Tuesday, December 19, 2017

QUESTION NO. 5

QUESTION: Councillor L. O'Toole

"To ask the Chief Executive to confirm that the timeline for the Lucan swimming pool is still in place and to provide any further updates?"

REPLY:

The Fire Safety and Disability Access Certificate applications were submitted on 13th October.

The Design Team are progressing well with the preparation of tender documents. Detail design of all the main elements is well advanced.

The Prequalification process for the main contractor and reserved specialists is due to commence early in December.

Final tender documents will be complete and requests for tender are due to be made at the end of February 2018.

The tender process will take six weeks to complete.

On conclusion of the tender process a Tender Report will be prepared and issued to the Department of Transport Tourism and Sport for final approval.  

Once this approval is received the Contractor will be appointed and work will begin. This start date is dependent on the Departments approval but is estimated at June 2018.

The project will take 12 – 18months to complete and fit out ready for operation by the end of 2019.