QUESTION NO. 8

QUESTION: Councillor C. O'Connor

"To ask the Chief Executive to confirm details in respect of housing accommodation currently construction under the area covered by the Tallaght Area Committee, will he confirm the schedule being followed and state when he expects such accommodation to be available for allocation?"

REPLY:

Current Social Housing Construction Programme.

The schemes listed below are scheduled for delivery from Q2 2018 and allocation of these units will be completed following handover of the units from the contractor. A total of 127 units will be delivered through the social housing build programme in 2018 with a further 27 scheduled in early 2019.

Future sites countywide are currently under review as options for social housing developments and proposed locations will be brought forward to the relevant Area Committees in early 2018 for consideration.

Schemes

No. of Units

Status

Due for Delivery Q1 2018

Due for Delivery  Q2 2018

Due for Delivery  Q3 2018

Due for Delivery  Q4 2018

Due for Delivery  Q1 2019

Mac Uilliam (Fortunestown)

28

On Site May 2017

 

 

28

 

 

Dromcarra, Tallaght

14

On Site May 2017

 

 

14

 

 

St. Aidans, Tallaght

85

On Site August 2017

 

66

19

 

 

Killinarden, Tallaght

27

On Site October 2017

 

 

 

 

27