"This Committee requests the Chief Executive provide an updated detailed report on the swimming pool for Lucan including confirmation that the timeline for completion remains as previously reported."
REPORT:
The Fire Safety and Disability Access Certificate applications were submitted on 13th October.
The Design Team are progressing well with the preparation of tender documents. Detail design of all the main elements is well advanced.
The Prequalification process for the main contractor and reserved specialists is due to commence early in December.
Final tender documents will be complete and requests for tender are due to be made at the end of February 2018.
The tender process will take six weeks to complete.
On conclusion of the tender process a Tender Report will be prepared and issued to the Department of Transport Tourism and Sport for final approval.
Once this approval is received the Contractor will be appointed and work will begin. This start date is dependent on the Departments approval but is estimated at June 2018.
The project will take 12 – 18months to complete and fit out ready for operation by the end of 2019.