QUESTION NO. 2

QUESTION: Councillor W. Lavelle

"To ask the Chief Executive for a timeline outlining the next stages of the Lucan Swimming Pool development project?"
 
 

REPLY:

The Architect’s report was presented at the September Council meeting and the Part 8 approved by Council. The Tender documents are now in preparation and it is envisaged that tenders will be sought in February of next year with a view to starting on site in April 2018. The duration of the contract on site will be in the region of 15 to 18 months.