COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN AREA COMMITTEE
Tuesday, October 24, 2017
QUESTION NO. 2
QUESTION: Councillor W. Lavelle
REPLY:
The Architect’s report was presented at the September Council meeting and the Part 8 approved by Council. The Tender documents are now in preparation and it is envisaged that tenders will be sought in February of next year with a view to starting on site in April 2018. The duration of the contract on site will be in the region of 15 to 18 months.