COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN AREA COMMITTEE
Tuesday, March 28, 2017
QUESTION NO. 7
QUESTION: Councillor L. O'Toole
"Could the Chief Executive confirm what is the total amount spent to date on design costs towards the Lucan swimming pool from the agreed €450,000 allocated to this project?"
REPLY:
A design team were appointed by the Council and this consists of Architectural, Quantity Surveyor, Structural and Civil Engineering and Mechanical and Electrical Engineering Consultants.
Payment will be made on a staged basis to the consultants and to date payment of €11,685 has been made.