The following play space and playground projects are planned to be progressed in 2017. Some have already commenced in terms of consultation, design and tendering. The refurbishment of the Griffeen Valley Playground will commence shortly once the tender standstill period has expired and a contract is awarded. Four projects commenced in 2016 are at an advanced stage and three (Kingswood, Kilnamanagh and Glendoher) are effectively opened. The playground in Tymon Park North will be opened in April 2017. In addition, it also proposed to commence design scoping for the refurbishment of the Corkagh Park playground.
LUCAN |
|
Location |
Update |
Griffeen Valley Park |
Tenders received and analysed. Recommendation made. Tender standstill period in place. Expected commencement May 2017 |
Lucan Demesne |
Design work to commence |
Newcastle Road area |
Consultation scoping commenced |
Hillcrest Estate Lucan |
Consultation to commence |
|
|
CLONDALKIN |
|
Neilstown area |
Consultation commenced |
Collinstown Park |
|
Bawnogue Area (including Cherrywood Park and St Cuthberts Park) |
Consultation to commence |
Boot Road |
Consultation to commence |
TALLAGHT CENTRAL |
|
Ballymount Park |
Consultation to commence |
|
|
TALLAGHT SOUTH |
|
Jobstown Park |
Design work commenced |
Saggart |
Consultation to commence |
|
|
TEMPLEOGUE TERENURE |
|
Delaford |
Consultation to commence |
Glendown Park |
Consultation to commence |
Perrystown |
Consultation commenced |
RATHFARNHAM |
|
Marian Road |
Consultation commenced |
Longwood/Stonepark Abbey Rathfarnham |
Consultation commenced |
Elkwood |
Consultation to commence |