COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF LUCAN AREA COMMITTEE
Tuesday, February 28, 2017
QUESTION NO. 16
QUESTION: Councillor P. Gogarty
"To ask the Chief Executive for a further progress report on step down housing site identification and/or construction prospects on existing Council owned sites in Lucan and Palmerstown; and if a statement can be made on the matter?"
REPLY:
The report to the Council Meeting in March 2015, set out proposals for Social Housing units for the period 2015 to 2017 in line with the Housing strategy as set out in the Governments “Social Housing Strategy 2020 – Support, Supply and Reform” published late November 2014.
Progress in relation to the rollout of the Part 8 Social Housing Programme countywide is as follows:
Project | Units | Current Stage |
St. Finians Avenue, Lucan | 2 | Construction Completed 2016 |
Suncroft, Tallaght | 10 | Construction Completed 2016 |
St Marks Green, Clondalkin | 11 | Construction contract awarded; due to commence Q1 2017 |
Fortunestown (MacUilliam) | 28 | Stage 4 Approval Received; due to commence construction Q1 2017 |
Mayfield Estate | 18 | Construction contract awarded; due to commence Q1 2017 |
Dromcarra, Tallaght | 14 | Stage 4 Approval Received; due to commence construction Q1 2017 |
Letts Field, Neilstown, Clondalkin | 37 | Tenders due early March. Assessment and recommendation to the Dept. to forward during March. |
Ballyboden, Rathfarnham | 40 | Tender package ready for tendering process. Final submission and approval in process for Stage 3. |
Killinarden, Tallaght | 28 | Tenders due early March. Contractor appointment due to follow assessment and submission to Dept. for approval. |
St. Aidans, Tallaght | 71 | Tenders have been submitted and are currently being assessed. Report on recommendation for Contractor Appointment to be issued in early March for Dept. approval. |
Killininny, Co Dublin | 24 | Design development of Tender Package to proceed with Stage 3 completed by April. |
St. Cuthberts, Clondalkin | 59 | Design development of Tender Package to proceed with Stage 3 completed by April. |
Oldcastle | 50 | Stage 1 submission in preparation, scheduled for submisssion to Dept. in late March. |
380 |
The March 2015 report identfied a number of additional sites throughut the county for Part 8 consideration including a site at Balgaddy F with potential capacity for 50 no. units.