COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, February 15, 2017
QUESTION NO. 6
QUESTION: Councillor F. Timmons
"To ask for a report into how many 1, 2, 3 and 4 bed units/homes are planned to be built in the Clondalkin area from 2017 to 2019?"
REPLY:
The breakdown of social housing units due to be built in the Clondalkin area over 2017-2019 are listed below.
- St. Marks Green and Mayfield are due to commence construction in the coming weeks with expected completion dates of March 2018.
- Letts Field is currently out to tender for contractors and pending final departmental budget approval will have a target of mid 2017 construction commencement.
- St. Cuthberts has 63 Rapid Build Units with Part 8 approval. Tender documents will now be prepared in respect of progressing the design/build tender for this project.
Project Name | Total No of Units | 3 bed/(4 person) | 3 bed/(5 person | 3 bed (5 person adaptable) | 3-4 bed/(6 person) | 4 Bed/6 Person | 2 bed (3-4 person | 1 bed | specially adapted | Practical Completion |
St Marks Green | 11 | 0 | 10 | 0 | 1 | 0 | 0 | 0 | 0 | Quarter 1 2018 |
Mayfield | 18 | 4 | 10 | 4 | 0 | 0 | 0 | 0 | 0 | Quarter 1 2018 |
St Cuthbert's Park, Clondalkin (Rapid Build Scheme) | 63 | 32 | 21 | 0 | 0 | 5 | 5 | 0 | 0 | Quarter 2 2018 |
Lett's Field SH380 | 48 | 18 | 25 | 0 | 4 | 0 | 0 | 0 | 1 | Quarter 4 2018 |
140 | 54 | 66 | 4 | 5 | 5 | 5 | 0 | 1 |