QUESTION NO.28
QUESTION: Councillor D. Richardson
"To ask the Chief Executive to report on current part 8s that have been passed across the county and report on delay of houses being built?"
REPLY:
"There are currently 8 projects which have been Part 8 approved and are at various stage of approvals. The Department of Housing Planning Community and Local Government (DHPCLG) have sanctioned all projects in principal and all are at various stages 1-4 of the Capital Works Management Framework. The status of each of the projects are as follows:
Project Name |
No. of Units |
Part 8 Granted |
Current Status |
St Marks Green, Clondalkin |
11 |
Sep-13 |
The Department of Housing Planning Community and Local Government (DHPCLG) have approved final contractor costs. Site Start February 2017 |
Fortunestown (MacUilliam) |
28 |
Mar-14 |
Pending Departmental approval of contract tender -target Q1 2017 construction start. |
Mayfield Estate |
18 |
Mar-14 |
The Department of Housing Planning Community and Local Government (DHPCLG) have approved final contractor costs. Site Start February 2017 |
Dromcarra, Tallaght |
14 |
Jun-15 |
Pending Departmental approval of contract tender -target Q1 2017 construction start. |
Letts Field, Neilstown, Clondalkin |
37 |
Sep-15 |
Project currently out to tender for contractors. Start date for construction will be dependent upon Departmental approval of contractor costs (Stage 4) |
Ballyboden, Rathfarnham |
40 |
Oct-15 |
Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – January 2017 |
Killinarden, Tallaght |
28 |
Nov-15 |
Project currently out to tender for contractors. Start date for construction will be dependent upon Departmental approval of contractor costs (Stage 4) |
St. Aidans, Tallaght -RAPID BUILD PROJECT |
85 |
Sep-16 |
Project currently out to tender for design/build contractor. |
Killininny, Tallaght – RAPID BUILD PROJECT |
24 (indicative) |
Pending |
Capital Appraisal and Approval to proceed to Planning received from Department of Housing (Stage 2 Approval). Part 8 report being presented to Council in February. |
St. Cuthberts, Clondalkin – RAPID BUILD PROJECT |
59 (Indicative) |
Pending |
Capital Appraisal and Approval to proceed to Planning received from Department of Housing (Stage 2 Approval). Part 8 report being presented to Council in February. |
Oldcastle, Clondalkin – RAPID BUILD PROJECT |
50 (Indicative) |
Pending |
Project currently in pre-planning |
|
394 |
|
|