"To ask the Chief Executive to report on current part 8s that have been passed across the county and report on delay of houses being built?"

REPLY: 

"There are currently 8 projects which have been Part 8 approved and are at various stage of approvals. The Department of Housing Planning Community and Local Government (DHPCLG) have sanctioned all projects in principal and all are at various stages 1-4 of the Capital Works Management Framework. The status of each of the projects are as follows:

Project Name

No. of Units

Part 8 Granted

 

 

 

 

Current Status

St Marks Green, Clondalkin

11

Sep-13

The Department of Housing Planning Community and Local Government (DHPCLG) have approved final contractor costs. Site Start February 2017

Fortunestown (MacUilliam)

28

Mar-14

Pending Departmental approval of contract tender -target Q1 2017 construction start.

Mayfield Estate

18

Mar-14

The Department of Housing Planning Community and Local Government (DHPCLG) have approved final contractor costs. Site Start February 2017

Dromcarra, Tallaght

14

Jun-15

Pending Departmental approval of contract tender -target Q1 2017 construction start.

Letts Field, Neilstown, Clondalkin

37

Sep-15

Project currently out to tender for contractors. Start date for construction will be dependent upon Departmental approval of contractor costs (Stage 4)

Ballyboden, Rathfarnham

40

Oct-15

Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – January 2017

Killinarden, Tallaght

28

Nov-15

Project currently out to tender for contractors. Start date for construction will be dependent upon Departmental approval of contractor costs (Stage 4)

St. Aidans, Tallaght -RAPID BUILD PROJECT

85

Sep-16

Project currently out to tender for design/build contractor.

 Killininny, Tallaght – RAPID BUILD PROJECT

24 (indicative)

 Pending

Capital Appraisal and Approval to proceed to Planning received from Department of Housing (Stage 2 Approval). Part 8 report being presented to Council in February.

St. Cuthberts, Clondalkin – RAPID BUILD PROJECT

59 (Indicative)

Pending

Capital Appraisal and Approval to proceed to Planning received from Department of Housing (Stage 2 Approval). Part 8 report being presented to Council in February.

Oldcastle, Clondalkin – RAPID BUILD PROJECT

50 (Indicative)

Pending

Project currently in pre-planning

 

394