QUESTION NO.20
QUESTION: Councillor F. Timmons
To ask for a report into RAPID housing ? how long does it take to build over time for a regular house? what is cost? how has tender been reached ? can SDCC apply out for a better priced tender?
REPLY:
The Council has gone to Tender in respect of 71 unit housing project together with option for 19 further units, at St. Aidan’s site, Brookfield Road / R136 Road, Tallaght, D24.The Tender is for a Design / Build Rapid Build Project. The time from other projects is for delivery within a timeframe which can be circa 10 months quicker than traditional build.
The time and cost of building a rapid built unit will be determined by public tender.