QUESTION NO.14

QUESTION: Councillor D. O'Brien

To ask the Chief Executive for a report on all the part 8s for housing that have been voted on in the council in the last two years. What stage are they are at present and how many are still waiting for funding from the government.

REPLY:

There are currently 8 projects which have been Part 8 approved and are at various stage of approvals. The Department of Housing Planning Community and Local Government (DHPCLG) have sanctioned all projects in principal and all are at various stages 1-4 of the Capital Works Management Framework. The status of each of the projects are as follows:

Project Name

No. of Units

Part 8 Granted

 

 

 

 

Current Status

St Marks Green, Clondalkin

11

Sep-13

Tender Complete – Awaiting Final DHPLG Stage 4 Approval. Target construction start Q1 2017

Fortunestown (MacUilliam)

28

Mar-14

Project currently out to tender for contractors. Pending Departmental approval of contract tender -target Q1 2017 construction start.

Mayfield Estate

18

Mar-14

Tender Complete – Awaiting Final DHPLG Stage 4 Approval. Target Q1 2017 construction start.

Dromcarra, Tallaght

14

Jun-15

Project currently out to tender for contractors. Pending Departmental approval of contract tender -target Q1 2017 construction start.

Letts Field, Neilstown, Clondalkin

37

Sep-15

Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016.

Ballyboden, Rathfarnham

40

Oct-15

Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016.

Killinarden, Tallaght

28

Nov-15

Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016.

St. Aidans, Tallaght -RAPID BUILD PROJECT

85

Sep-16

Project currently with the Department for pre-tender approval (Stage 2). Upon receipt of Stage 2 approval SDCC will go to tender for design/build contract – target December 2016.

 

261