COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL
MEETING OF SOUTH DUBLIN COUNTY COUNCIL
Monday, December 12, 2016
QUESTION NO.14
QUESTION: Councillor D. O'Brien
To ask the Chief Executive for a report on all the part 8s for housing that have been voted on in the council in the last two years. What stage are they are at present and how many are still waiting for funding from the government.
REPLY:
There are currently 8 projects which have been Part 8 approved and are at various stage of approvals. The Department of Housing Planning Community and Local Government (DHPCLG) have sanctioned all projects in principal and all are at various stages 1-4 of the Capital Works Management Framework. The status of each of the projects are as follows:
Project Name |
No. of Units |
Part 8 Granted |
Current Status |
St Marks Green, Clondalkin |
11 |
Sep-13 |
Tender Complete – Awaiting Final DHPLG Stage 4 Approval. Target construction start Q1 2017 |
Fortunestown (MacUilliam) |
28 |
Mar-14 |
Project currently out to tender for contractors. Pending Departmental approval of contract tender -target Q1 2017 construction start. |
Mayfield Estate |
18 |
Mar-14 |
Tender Complete – Awaiting Final DHPLG Stage 4 Approval. Target Q1 2017 construction start. |
Dromcarra, Tallaght |
14 |
Jun-15 |
Project currently out to tender for contractors. Pending Departmental approval of contract tender -target Q1 2017 construction start. |
Letts Field, Neilstown, Clondalkin |
37 |
Sep-15 |
Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016. |
Ballyboden, Rathfarnham |
40 |
Oct-15 |
Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016. |
Killinarden, Tallaght |
28 |
Nov-15 |
Project currently with the Department for pre-tender approval (Stage 3). Upon receipt of Stage 3 approval SDCC will go to tender for contractors – target December 2016. |
St. Aidans, Tallaght -RAPID BUILD PROJECT |
85 |
Sep-16 |
Project currently with the Department for pre-tender approval (Stage 2). Upon receipt of Stage 2 approval SDCC will go to tender for design/build contract – target December 2016. |
|
261 |
|
|