QUESTION NO. 1
QUESTION: Councillor M. Duff
"To ask the Chief Executive to make a report to this Committee regarding the status of the Tallaght Village Improvement Scheme and can he update this Committee on any review of the Scheme and where it is at now?"
REPLY:
"There are three main elements to this scheme:
1. Old Greenhills Road Upgrade: The design for this has been completed, including the undergrounding of ESBN Overheads, new footpaths, new public lighting and a new pedestrian plaza linking the old and new Greenhills Rd at the northern end of the cul de sac.
2. Main Street Plaza: This is the upgrade of the pedestrian area at Macari's opposite the Dragon Inn. Final design on this element is currently underway.
3. Public Lighting Upgrade on Old Bawn Rd: This is an upgrade of the existing lighting between Main Street Plaza and the N81. The design for this is complete.
It is intended to combine all three elements above into the one tender and this will be issued in early 2017."